Kennedy Space Center

SpaceX launched NASA’s Nancy Grace Roman Space Telescope Sunday morning aboard Falcon Heavy. Liftoff was at 7:26 am ET from LC-39A at Kennedy Space Center. And seven and a half minutes later, the day got off to a booming start for many on the Space Coast today when a pair of sonic booms echoed across the area just as they landed at Cape Canaveral Space Station.

Read more

The launch of Artemis II is coming soon at Kennedy Space Center, and it is going to be unlike anything most people have seen in their lifetimes. The last time a crewed moon rocket launched from this pad at Kennedy was Apollo 17 in December 1972, and the Space Launch System is even more powerful than the Saturn V that carried those astronauts to the Moon. The plumes will be blinding, the sound will rattle your chest and your car windows, and the moment will be etched in your memory forever. If you are a photographer, you have a once-in-a-generation opportunity to document history.

NASA’s Space Launch System rocket carrying the Orion spacecraft launches on the Artemis I flight test, Wednesday, Nov. 16, 2022, from Launch Complex 39B at NASA’s Kennedy Space Center in Florida. NASA’s Artemis I mission is the first integrated flight test of the agency’s deep space exploration systems: the Orion spacecraft, Space Launch System (SLS) rocket, and ground systems. SLS and Orion launched at 1:47am ET from Launch Pad 39B at the Kennedy Space Center.
NASA/Bill Ingalls
Read more

Artemis II, earlier this month at Kennedy Space Center
Photo: Charles Boyer

NASA is moving ahead with a second wet dress rehearsal, or WDR-2, for the Artemis II mission. Launch controllers will take their positions in the Launch Control Center at 6:40 PM ET tonight (Feb. 17), kicking off a nearly 50-hour countdown sequence. The simulated launch window opens at 8:30 PM on February 19th and extends four hours.

Read more

artemis II Photo by Charles Boyer

When NASA wrapped up the first Artemis II wet dress rehearsal on February 3 at Kennedy Space Center, they had successfully filled the SLS rocket’s tanks with cryogenic propellant. That was the good news, but the less welcome bad news was that the test revealed higher-than-allowable hydrogen gas leaks at the Tail Service Mast Unit on the launch pad. Obviously, those leaks must be repaired before a launch attempt.

NASA Stream from the first Wet Dress Rehearsal indicated full LH2 and LOX tanks on SLS. Credit: NASA

The Work For WDR-2 Started As Soon As WDR-1 Was Completed

Not long after propellant draining was complete after WDR-1, technicians began working to access the TSMU umbilical. They detached both the rocket-side and ground-side interface plates to inspect the area where elevated hydrogen levels were detected, and replaced seals around two fueling lines.

The two tail service masts — each about three stories tall — provide the cryogenic propellant lines and electrical cable connections to the SLS core stage. They tilt back before launch and include “quick disconnects” — mechanisms that instantaneously detach at liftoff to ensure safe retraction.

Reconnecting the interfaces is expected to be complete by Monday, Feb. 9. Engineers are still evaluating the root cause of the leak, and the removed seals are being analyzed. NASA also plans additional testing at Stennis Space Center in Bay St. Louis, Mississippi, to evaluate the dynamics of the interface plates. Engineers are reviewing options to verify the repair before committing to the next full wet dress rehearsal.

Repairs For WDR-2

Here’s a breakdown of the repairs underway and the operational changes NASA is making for WDR-2:

Five Key Changes for the Next Rehearsal
Five Key Changes for the Next Rehearsal
Artemis II Wet Dress Rehearsal  |  Kennedy Space Center
Type Change Details
Hardware Fix Two seals replaced Seals replaced around fueling lines at the tail service mast umbilical where hydrogen concentrations exceeded allowable levels. Removed seals are being analyzed and additional plate dynamics testing is planned at Stennis.
Operations Orion hatch closed before test The crew module hatch will be sealed prior to the rehearsal. The closeout crew — who on launch day help astronauts into their seats and close both Orion hatches — will not be deployed to the pad.
Operations Crew access arm stays extended The arm will not be retracted during the next rehearsal. Engineers successfully demonstrated during the Feb. 3 test that the ground launch sequencer can retract it during the final countdown phase, so that objective is already complete.
Timeline One extra hour in countdown NASA has added 30 minutes of extra hold time at each of two planned holds — one before and one after tanking operations — to allow more time for troubleshooting. The total countdown is now one hour longer. This does not affect the crew’s launch-day timeline.
Focus Shift Rehearsal focused on fueling With the crew access arm retraction and other pad objectives already demonstrated, the next WDR will concentrate on tanking operations and verifying the hydrogen leak repair.

Source: NASA, “NASA Conducts Repairs, Analysis Ahead of Next Artemis II Fueling Test,” Feb. 8, 2026

NASA continues to eye March as the next potential launch opportunity but will not set a targeted launch date until after completing a successful wet dress rehearsal and reviewing the data. The critical second WDR is set to start as soon as this Friday, February 13th.